. | |
Description: | Complete new installation of the fire alarm system incl. planning. |
Construction start: | July 2000 |
Construction time: | 3 months |
Client: | OSCE-Vienna |
ELCON contract: | Complete new installation of the entire fire alarm control panel from the manufacturer Esser. Including the complete power network, hand detector, central office, etc. |
Special features: | The OSCE building continued to operate throughout the installation. Most of the work had to be done after the end of the service. |