Description: | Complete planning and execution of the electrotechnical installation except fire alarm system and light current engineering. |
Project volume: | Approx. 4,8 million DM |
Construction start: | December 2000 |
Construction time: | Approx. 11 months |
Client: | Hotel Hilton |
General contractor: | ELCON GmbH |
ELCON contract: | Complete planning including matching the project documentation with the organizations which participated |
Special features: | Planning, obtaining the approvals and complete installation work had to be accomplished within a very short time. |