Construction project: | Building a facility in Kaluga with paint line, pressing plant next to the existing plant |
Client: | Benteler automotive |
Start of construction: | April/May 2011 |
ELCON constructions: | 7 months |
Scope of services: | In the framework of this project, ELCON was with the topics of electrical engineering, network engineering, installation of the stark- and low-voltage network addresses. |
| The following services are running:
|
Special features: | The provision was a period of about 7 months |