Construction project: | Headquarter General Motors in Moscow |
Description: | Complete interior fittings of the Northern Tower 9th and 10th floors with an effective area of about 4,500sq. meters. |
Project volume: | 4,5 million Euro |
Client: | General Motors Vehicles |
Start of construction: | 2008 |
Construction time: | Ca. 3 months |
Period of installation: | Ca. 6 months |
ELCON Contract: | Building services engineering on 9th and 10th flor of the Northern Tower |
Scope of services: | ELCON was the general contractor.
The following services were provided:
|
Special features: | Building services had to be provided within a period of 3 months. |