Project: | German embassy and Visa agency in Moscow 2002 |
Project volume: | Building service approx. 1,1 million Euro |
Construction start: | October 2002 |
Construction time: | 16 months |
Client: | Federal Office of building- and room planning |
General constructor: | Heitkamp GmbH |
ELCON contract: | Execution of the complicated building technology, including heating, air conditioning, ventilation, plumbing, |
Period of installation: | Only 5 months for the complete construction in Russian winter. |
Special features: | Complete skeleton construction of the exterior walls, interior construction lightweight construction |