Project: | German embassy in Sofia |
Description: | Renovation of the embassy building |
Construction start: | 15. September 1997 |
Construction time: | 6 weeks |
Client: | German Foreign Ministry |
General contractor: | Co. Bautech GmbH Uetze |
ELCON contract: | Renovation of ceiling lighting |
Special features: | The implementation was not allowed to interfere with the ongoing operation in the embassy. |