The SOS - Children´s Village Zanzibar is situated about 7 km out of the seaport Zanzibar. On an area of 6 hectare 4 buildings, 1 school, 1 nursery school and a general-purpose building were erected and equipped with required electrical building services by ELCON. It took only five weeks to complete the project although it was in the middle of the rainy season. |
|
|
| |
Project: | SOS Children’s village in Zanzibar |
Description: | 4 buildings, 1 school, 1 nursery school and various shops on an area of 6 hectare. |
Project volume: | Approx. 5 million US $ |
Construction start: | May 1997 |
Construction time: | Approx. 1,5 years |
Client: | SOS – Children’s Village International |
General contractor: | Co. Bautech GmbH Uetze |
ELCON contract: | Installation of complete electrical infrastructure. |
Period of installation: | 5 weeks |
Special features: | The work was severely affected by rainy season. |