Project: | European commercial bank in Moscow |
Description: | To accommodate a modern, western-equipped bank, a 100-year-old building was completely modernized and extended. |
Project volume: | 12,5 million DM |
Construction start: | December 1994 |
Construction time: | 13 months |
Client: | European commercial bank Moscow |
General contractor: | Strojservice GmbH Moscow (Hochtief Holding company) |
ELCON contract: | Planning and complete execution of all electrical and communication systems such as: low-voltage supply systems, outdoor lighting, interior and emergency lighting, telephone and call systems, fire alarm systems, access control system, burglar alarm system incl. safe protection, video surveillance system and lightning protection. |
Period of installation: | 10 months |
Special features: | The work should be carried out while the banking operation is ongoing and maintained. The extremely frequent rescheduling was very well mastered by our CAD-supported planning. |