Project: | Brewery Susyndar in Almaty |
Construction start: | January 2003 |
Construction time: | Approx. 2 months |
Client: | Brewery Susyndar |
General constructor: | Co. Huppmann |
ELCON contract: | Installation of all process technology responsible for the brewing process based on SIMATIC from Siemens. |
Period of installation: | Approx. 2 months |
Special features: | Very tight deadline stake and extreme climatic conditions for outdoor work ( -40°C ). |
Process engineering: Installation of the entire process control based on SIMATIC technology from Siemens under sometimes extreme conditions at outside temperatures of up to -40°C